1. The construction unit entrusts the monitoring institution to carry out the monitoring and prepare the monitoring report;
2. The construction unit shall submit the acceptance application report to the acceptance organization;
3. The environmental protection department shall review the data submitted by the construction unit (if the information is not
The reasons for not accepting the application shall be fully issued, and the acceptance shall be accepted if the conditions are met);
4. The environmental protection department shall carry out the preliminary review (within 5 working days) for the accepted projects, including report review and on-site verification;
5. Organize relevant departments to conduct on-site inspection and review, including review and review
The construction unit shall be informed of the unqualified rectification within 10 days;
6. The person in charge of the environmental protection agency shall review the acceptance;
7. The acceptance opinions are to be made public (5 working days). If the acceptance is unqualified, relevant materials shall be returned and accepted again after rectification;
8. Handle the acceptance approval documents and make them public.
Flow chart attached

?